Gangway repair covers the inspection, structural repair, corrosion treatment, load testing and recertification of a vessel's means of embarkation and disembarkation, including accommodation ladders, brows, shore gangways and their winches. Under SOLAS regulation II-1/3-9 and the IMO guidelines in MSC.1/Circ.1331, gangways must be inspected and maintained at appropriate intervals by a competent person, normally monthly as part of the planned maintenance system, with a full operational load test at the maximum operational load every five years. Most gangways that look scrap are repairable: cracked stringers, corroded treads, worn pivot pins, seized turntables and failed winch bed plates can all be rebuilt in a fabrication shop for a fraction of the cost of a new unit, usually inside one to three weeks.
Gangways get ignored right up until the moment a surveyor stops the ship. Here is how to stay ahead of that.
What counts as a gangway?
The terminology gets used loosely, and it matters because different standards apply to different pieces of kit.
| Equipment | What it is | Governing standard |
|---|---|---|
| Accommodation ladder | Ship mounted, stowed against the hull, lowered to the quay or a boat | ISO 5488:2015 |
| Shore gangway | Aluminium or steel walkway from quay to deck | ISO 7061 |
| Accommodation ladder winch | The winch, sheaves and brake that lower and hoist the ladder | ISO 7364:2016 |
| Brow | Heavier fixed or portable ramp, often used in dockyards and on RoRo | Class and yard rules |
| Gangway stacker or tower | Shore side structure supporting the gangway | LOLER and structural design |
| Pilot ladder | Rope and timber ladder for pilot transfer | SOLAS V/23 and separate regime |
The common thread is that all of it is a means of access, and all of it is load bearing with people on it. That is exactly why surveyors and port state control take it seriously.
What standards apply to gangways and accommodation ladders?
Four things sit behind almost every gangway conversation in the UK.
SOLAS regulation II-1/3-9. Means of embarkation and disembarkation must be provided and must be inspected and maintained at appropriate intervals to keep them fit for purpose, taking account of any loading restriction.
MSC.1/Circ.1331. The IMO guidelines for construction, installation, maintenance and inspection or survey of means of embarkation and disembarkation. This is the document that sets the practical inspection expectations most surveyors work to.
ISO 5488:2015, ISO 7061 and ISO 7364:2016. Accommodation ladders, aluminium shore gangways and accommodation ladder winches respectively. Ships built on or after 1 January 2010 should have equipment meeting these applicable international standards.
LOLER 1998, for shore side equipment in Great Britain. If the gangway or its tower is quayside equipment lifting people, thorough examination by a competent person applies. Equipment used to lift people is examined every six months, other lifting equipment every twelve.
That last one catches port operators out regularly. A ship's accommodation ladder sits in the SOLAS and class regime. A quayside gangway tower on your own berth is your lifting equipment, and the Health and Safety Executive will treat it as such.
How often does a gangway need inspecting and load testing?
Here is the practical schedule most operators run.
| Activity | Typical interval | What it covers |
|---|---|---|
| Visual inspection by crew | Before each use | Treads, handrails, stanchions, obvious damage, safety net rigged |
| Documented inspection by competent person | Monthly, in the planned maintenance system | Structure, wires, sheaves, brake, fittings, greasing |
| Wire rope inspection and renewal | Per manufacturer, commonly annual inspection | Broken wires, corrosion, terminations |
| Thorough examination (shore equipment, LOLER) | 6 months for lifting people, 12 months otherwise | Competent person examination and report |
| Full operational load test | Every 5 years | Test at maximum operational load, plus winch brake, power supply and remote control |
| Static and dynamic testing | Every 5 years alongside the above | Pilot, accommodation, embarkation and wharf ladders |
The five yearly test is the one that exposes deferred maintenance. Brakes that hold an empty ladder do not always hold a loaded one, and that is precisely what the test is there to find.
We carry out proof load testing on board as part of gangway packages, which means the repair and the recertification happen in one mobilisation rather than two.
What actually fails on a gangway?
From the units that come through our workshops, the failure list is remarkably consistent.
- Cracked stringers and side frames. Usually at the top pivot or at a weld toe, driven by fatigue from repeated hoisting and from the ladder swinging against the hull in a swell.
- Corroded treads and tread pins. Water and grit collect in the tread pockets. Aluminium treads go chalky and lose section, steel treads pit.
- Worn pivot pins and bushes. The single most common cause of that alarming rattle when the ladder is lowered.
- Rope sheaves and bearings. Seized sheaves chew wire ropes and then the wire fails the next inspection.
- Winch bed plates and turntable foundations. Cracks and distortion here are structural and need cutting out and replating, not welding over.
- Handrails, stanchions and net attachment points. Bent, missing or repaired badly by someone in a hurry.
- Non slip surfaces worn smooth. Not glamorous, and the most common cause of an actual injury.
If you only inspect one thing properly this month, make it the winch bed plate and the supporting structure for the sheaves and turntable. Cracks and distortion there are what turn a maintenance job into a dropped ladder.
Should you repair or replace a gangway?
New units have long lead times and eye watering prices, especially for anything with a bespoke geometry or a class approved winch. Refurbishment is usually the better economics. Usually, not always.
| Situation | Repair | Replace |
|---|---|---|
| Localised cracking at pivots or weld toes | Yes, cut out and replate | No |
| Corroded treads and handrails, sound frame | Yes, straightforward renewal | No |
| Worn pins, bushes, sheaves, wires | Yes, wear parts | No |
| Winch bed plate cracked, frame sound | Yes, replate and reinforce | No |
| Generalised section loss across the stringers | Marginal, get it measured | Likely yes |
| Original geometry no longer suits the berth | No | Yes, redesign |
| No documentation, unknown provenance, unknown SWL | Only with a full survey and recertification | Often yes |
The deciding question is not "how bad does it look". It is "how much sound parent material is left, and can we prove the repaired unit to its rated load afterwards". Ultrasonic thickness readings answer the first. A witnessed load test answers the second.
Aluminium or steel: does it change the repair?
Yes, significantly, and it is where a lot of cheap gangway repairs go wrong.
Most shore gangways are aluminium for weight. Aluminium welding needs different procedures, different filler selection, different pre cleaning and coded welders qualified for the alloy group. Heat treatment history matters too, because welding a heat treated aluminium alloy softens the heat affected zone whether you like it or not, so the repair has to be detailed with that in mind rather than just filled with weld.
Steel gangways and accommodation ladders are more forgiving to weld but far less forgiving about corrosion. Where a steel ladder meets aluminium fittings, or where stainless fasteners sit in aluminium, galvanic corrosion quietly eats the joint from the inside. Isolation washers and correct fastener selection are cheap. Replacing a stringer is not.
Either way, the welds on a repaired gangway should be inspected properly rather than eyeballed. Our guide to MPI weld testing and magnetic particle inspection covers what an inspector is actually looking for on a structural repair like this.
What a proper gangway refurbishment package includes
When we quote a refurbishment, this is the scope. Use it as a checklist when you are comparing quotes, because the cheap ones usually leave out half of it.
- Survey and thickness readings. Establish what is actually left before pricing repairs.
- Strip down. Treads, handrails, stanchions, netting, wires, sheaves, pins and bushes off.
- Structural repair. Crack excavation, insert plates, stringer sections renewed, winch bed plate and turntable foundation repairs.
- Weld inspection. Visual plus NDT on structural welds.
- Wear parts renewed. Pins, bushes, sheaves, bearings, wire ropes and terminations.
- Surface preparation and coating. Blast, prime and paint for steel, or appropriate treatment for aluminium. Non slip surfaces reinstated.
- Winch and controls. Brake overhaul, gearbox check, motor and control system tested. Electrical work on winch controls and gangway lighting sits with our marine and industrial electrical engineers.
- Reassembly and function test. Hoist, lower, rotate, brake hold.
- Load test and certification. Tested to the rated load, with a certificate and a report the surveyor will accept.
- Documentation. Updated drawings, SWL marking, and a record for the planned maintenance system.
Number ten is the one people skip and then regret. If the SWL plate is missing or unreadable, half your compliance problem is the paperwork rather than the steel.
How long does gangway repair take, and how do you avoid the vessel waiting?
Realistic timescales, assuming the unit can be landed ashore.
| Scope | Typical duration |
|---|---|
| Emergency crack repair in situ to allow safe use | Same day to 48 hours |
| Wear parts, wires and treads renewed ashore | 3 to 7 days |
| Full strip, structural repair, coat and load test | 1 to 3 weeks |
| Fabrication of a new bespoke gangway or stacker | 4 to 10 weeks |
The way to avoid a vessel sitting is to plan the refurbishment around a repair period you are already having, or to land the gangway on one call and refit it on the next. Where the unit genuinely cannot come off, we mobilise for on site and shipboard welding and do the structural work in place, which is slower per hour but far quicker overall than losing the berth.
We have done both. A cracked ship gangway repaired and reinstalled, an emergency gangway repair and replacement where the vessel had a sailing date, a gangway stacker rebuilt at Falmouth and material gangways supplied out of Peterlee. Those jobs are on our projects pages if you want to see the before and after.
Where EAP Ltd covers
Gangway repair, refurbishment, load testing and new build fabrication are available 24 hours a day, 365 days a year across our UK network, including Chatham and the Medway, Southampton, Plymouth, Falmouth, Hull and the Humber, Peterlee, the North East and the Tyne, Rosyth and Glasgow, plus EU coverage from our Constanta base.
Because we run marine fabrication, structural steel fabrication, mechanical and electrical teams under one roof, a gangway job does not get handed between three contractors. The welders, the fitters overhauling the winch and the electricians on the controls are the same company, working to one programme.
Got a gangway that has failed an inspection, or one you know will not pass the next one? Send us photos and the last inspection report. Request a gangway repair quote from EAP Ltd or call +44 (0)1634 827369, and tell us your sailing date so we can work backwards from it.
Frequently asked questions
How often does a ship's gangway need to be inspected?
Under SOLAS regulation II-1/3-9 and the IMO guidelines in MSC.1/Circ.1331, means of embarkation and disembarkation must be inspected and maintained at appropriate intervals. In practice that means a visual check before each use by the crew, a documented monthly inspection by a competent person within the planned maintenance system, and a full operational load test at the maximum operational load every five years.
How often does a gangway need a load test?
Every five years the equipment should be operationally tested at its specific maximum operational load, with the winch brake system, power supply and remote control system examined and load tested at the same time. Static and dynamic testing of accommodation, embarkation, pilot and wharf ladders is carried out on the same cycle. Shore side gangway equipment in Great Britain that lifts people also falls under LOLER thorough examination every six months.
Can a cracked gangway be repaired, or does it have to be replaced?
Most cracked gangways can be repaired. Localised cracking at pivots, weld toes and winch bed plates is normally cut out and replated. Replacement becomes the better option when there is generalised section loss across the stringers, when the geometry no longer suits the berth, or when there is no documentation to establish the original safe working load. Ultrasonic thickness readings and a witnessed load test are what settle the decision.
What standards apply to accommodation ladders and shore gangways?
Accommodation ladders are covered by ISO 5488:2015, aluminium shore gangways for seagoing vessels by ISO 7061, and accommodation ladder winches by ISO 7364:2016. Ships constructed on or after 1 January 2010 should have equipment meeting these applicable international standards, alongside SOLAS regulation II-1/3-9 and the guidelines in MSC.1/Circ.1331.
What usually fails first on a gangway?
Pivot pins and bushes, tread corrosion and cracking at weld toes on the stringers are the most common findings. Structurally the most serious findings are cracks and distortion in the winch bed plate and in the supporting structure for the sheaves and turntable, because failure there can drop the ladder.
Do you repair aluminium gangways as well as steel ones?
Yes. Aluminium repair needs coded welders qualified for the alloy group, correct filler selection and careful detailing around the heat affected zone, because welding a heat treated aluminium alloy softens the material locally. Galvanic corrosion at joints between aluminium, steel and stainless fasteners is a common secondary problem and is addressed with correct fastener selection and isolation.
How long does a full gangway refurbishment take?
An emergency crack repair to allow safe use can be same day to 48 hours. Renewing wear parts, wires and treads ashore is typically three to seven days. A full strip down, structural repair, recoat and load test runs one to three weeks. Fabricating a new bespoke gangway or stacker is four to ten weeks.
Can gangway work be done alongside, or does the vessel need to be in dry dock?
Alongside is normal. Gangway work rarely requires dry docking, since the unit can usually be landed ashore and returned, or repaired in place with on site welding. It is often bundled into a repair period that is already planned for other reasons.